碾压沙漠砂贫混凝土治理变电站地基塌陷
(1.宁夏超高压电力工程有限公司,宁夏 银川 750001;2.宁夏跃元工程有限公司,宁夏 固原 750000;3.北方民族大学机电工程学院,宁夏 银川 750021)
Foundation Collapse of Crushed Desert Sand-poor Concrete
(1.Ningxia Ultra High Voltage Power Engineering Co., Ltd, Yinchuan 750001, Ningxia, China;2.Ningxia Yueyuan Engineering Co.Ltd, Guyuan 750000, Ningxia, China;3.School of Electromechanical Eng., North Minzu University, Yinchuan 750021,Ningxia,China)
摘要
图/表
参考文献
本刊相似文献
All Journals 相似文献
All Journals 引证文献
本文已被:浏览 1092次   下载 2347
投稿时间:2021-04-28    
中文摘要:
Abstract:Helanshan 750 kV substation is one of the main grid structure of Ningxia 750 kV and the bridge of power transmission in Ningxia Dam Power Plant. In the years after its completion and operation, some common substation foundation diseases have appeared. The reason is not the early design or construction problem, but the traditional filling method can not be tamped, and the traditional backfill has poor scour resistance, which leads to uneven settlement and erosion induced collapse.
文章编号:20210407     中图分类号:TU433;TM63
基金项目:北方民族大学校企联合横向项目(2102000247)
引用文本: 王宏涛,杨宝平,杜伊,康亚明.碾压沙漠砂贫混凝土治理变电站地基塌陷[J].铜业工程,2021,(4):29-32